Phase Two of the project, which is the provision of the power station infrastructure ready for delivery of the generator sets, is well underway. The site office facilities and amenities buildings are approaching completion and the steel frame for the workshop building has been erected. Installation of the external cladding for the workshop building is due to conclude next week.
Tenders have now been requested for both construction of the control room and also for the building that will house all three Dual-Fuel Generator Sets. Manufacture of the radiator cooling system is underway in Adelaide and will be assembled and tested prior to being dispatched to the Owen Springs site.
Phase Two of the project is due for completion in May 2010.