A significant milestone in the project was reached when the first of the three 11MW generator units was loaded onto the ship in Saint Nazaire in France in February 2010, due for arrival in Darwin in early April. Each 276 Tonne generator set will be transported to site using multiple prime movers and a low loading trailer, taking some 6 days via a carefully investigated 1500km route to the site near Alice Springs.
The first generator set is scheduled to be commissioned in July with the complete power station to be handed over to Power and Water corporation in October 2010.
Once operational, the 33MW Owen Springs Power station will provide the highest efficiency open cycle power in Australia.
Written by Michael Masters, Power Plant Sales Engineer, MAN Diesel Australia